Modbury Sporting Club building and sportsfield lighting
- Project typeCapital works
- Project value$5 million
- Project schedule2024 completion
A new $5 million club room facility is on the way for Modbury Sporting Club at Ridgehaven.
Construction will begin in mid-to-late 2023 and will include four unisex change rooms, umpire rooms, function space and amenities.
Modbury Sporting Club consists of the Modbury Football and Modbury Cricket clubs, which has more than 700 players and members.
The new facility will enable the sporting club to better cater for further growth. The club’s members play cricket and football at senior and junior levels in both male and female competitions.
The works, scheduled for completion in late 2024, will be funded by Tea Tree Gully Council ($1.12 million) and the State Government ($3.87 million).
See the redevelopment plans and concepts(PDF, 3MB). A render of the Modbury Sporting Club building is below.

Project schedule
Design: Mid 2022 to mid 2023
Construction Tender: Mid 2023
Construction: Mid 2023 to mid 2024
Complete: Mid 2024.
Location
Hazel Grove, Ridgehaven View Map
-34.8220632,138.7023087
Hazel Grove ,
Ridgehaven