Update on $2.2 million upgrade of One Tree Hill Road

Published on 26 July 2021

one tree hill.jpg

Update 6 October 2021
Project delayed: Works have been delayed due to COVID-19 restrictions, weather and shortage of materials. Expected completion date is now November 2021. 


Be on the look out for roadworks on One Tree Hill Road at Gould Creek.

A 2.6 kilometre section, between Hannaford Hump and Shillabeer roads, will be reconstructed through the Special Local Road Program at a cost of $2.2 million.

The road will also be widened, plus new line marking and signs installed to improve road safety. 

Work is progressing, with the road now open to vehicles. However, traffic controls will remain in place until works are completed. Please try to avoid the area if possible.  

This is a joint project by the cities of Tea Tree Gully and Playford.