Published 24 November 2017

Tea Tree Gully Council has completed almost 7 km of reseal and reconstruction works to more than 23 roads as part of the $4 million in planned road improvements for 2017-2018.

And the good news is there are still more road upgrades on the way.

The suburbs to benefit from the scheduled works are Dernancourt, Gilles Plains, Greenwith, Golden Grove, Highbury, Holden Hill, Modbury and Modbury North.

See below for a list of completed and planned works.

Remember, you can always report a pothole, damaged kerb, or a missing or damaged roadway sign online 

 

Road reseals

Completed

Holden Hill
  • Abbey Close
  • Alvis Crescent
  • Bentley Drive
  • Brabham Avenue
  • Dawe Street
  • Elliot Avenue (from The Parkway to end)
  • Falcon Street
  • Karina Crescent
  • Karina Court
  • Malcom Avenue
  • Morgala Drive
  • McKinley Court
  • Riley Street
  • Simca Street
  • Southern Terrace
  • The Driveway (from Malcolm Avenue to McBean Avenue)
  • The Parade
  • The Parkway (from The Parade to Southern Terrace)
  • Waninga Drive
Modbury
  • Duchess Street
  • Princess Drive

To commence

Holden Hill
  • Cortina Avenue
Dernancourt
  • Scot Road (from Beck Street)
Highbury
  • Declivity Street
  • Monticle Street
Modbury
  • Cooke Street
  • Pierre Drive
Modbury North
  • Kelly Road (from Montague Road to Milne road)

 

Road reconstructions

Completed

Gilles Plains
  • Newcombe Drive

Modbury

  • Welloch Street

In progress

Greenwith
  • Ballard Close
  • Dalrymple Way

To commence

Golden Grove
  • Pineridge Court
  • Elmwood Rise
Modbury Heights
  • Melrose Street

Completed and planned footpath improvements.

Tags