Published 06 February 2019

With 590 km of sealed roads in the City of Tea Tree Gully, it’s little wonder roads are once again a big ticket item in our recently approved annual budget.

More than $3 million will be invested in road upgrades and renewals to improve safety for drivers and pedestrians in the 2018-2019 financial year.

Roadworks scheduled for 2018-2019

 This list is updated quarterly 
Road reconstruction -  $1.8 million

Resealing/road kerbing - $1.2 million 

Re-sheeting unsealed roads - $126,000

Roads to Recovery - $197,000

Road reconstruction - $1.8 million

Roads are reconstructed when they are not suitable to be repaired as they have developed structural faults

Holden Hill

  •  Graham Avenue - The Driveway to The Parade - completed
  •  Mercedes Drive - Bentley Drive to McKinley Avenue - completed

Modbury Heights

  •  Taurus Crescent - Noya Avenue - completed

St Agnes

  • Barton Court - Curtin Avenue to end - completed

Wynn Vale

  • Alicante Avenue - Park Lake Drive to Shiraz Street - deferred until 2019-2020 financial year

Resealing/road kerbing - $1.2 million

Resealing roads extends their life and improve safety and viability

Banksia Park

  • Magnolia Court - Milne Road to end - completed

Dernancourt

  • Heathfield Avenue - Parsons Road to end - completed
  • Glenwood Walk - Parsons Road to end - completed
  • Parsons Road -  Lyons Road to Cedar Avenue - completed

 Highbury

  • Combe Place -  Hillside Avenue to end - completed
  • Conifer Place - Historic Drive to end - completed
  • Crown Road - Dene Road to Country Lane - completed
  • Dene Road - 1056 Lower North East Road to 1110 Lower North East Road - completed
  • Dinham Court - Historic Drive to end - completed
  • Garden Court - Historic Drive to end  - completed
  • Historic Drive - Hillside Avenue to end - completed
  • Konos Place - Woodland Court to end - completed
  • Moon Crescent -  Dene Road to end - completed
  • Perrin Street - Crown Road to end - completed
  • Pioneer Court - Historic Drive to end - completed
  • Sun Crescent - Dene Road to end - completed
  • Torrens View Court - Historic Drive to end - completed
  •  Woodland Court - Historic Drive to end - completed

Holden Hill

  •  Mercedes Drive - McKinley Avenue (Mercedes Drive to Valiant Road) - completed

Hope Valley

  • Battarbee Street - Heysen Avenue to end - completed
  • Boyd Court - Dargie Avenue to end - completed
  • Dargie Avenue - Streeton Avenue to Dobell Court - completed
  • Dobell Court - Dargie Avenue to end - completed
  • Dowie Court - Battarbee Street to end - completed
  • Gill Court - McCubbin Avenue to end - completed
  • Honeysuckle Drive - Valley Road to Payne Street - completed
  • McCubbin Avenue - Namatjira Avenue to Pro Hart Court - completed
  • Namatjira Avenue - Streeton Avenue to McCubbin Avenue - completed
  • Nolan Court - Dargie Avenue to end - completed
  • Richmond Road - Boronia Drive to Irene Avenue - completed
  • Robin Terrace - Boronia Drive to Irene Avenue - completed
  • Streeton Avenue - Heysen Avenue to end - completed
  • Tucker Street -  Heysen Avenue to Namatjira Avenue - completed
  • Waratah Drive -  Irene Avenue to Honeysuckle Drive - completed

Tea Tree Gully

  •  Ellen Street, Tea Tree Gully – Milne Road to Julia Street - completed
  • Harding Street, Tea Tree Gully – William Street to Walter Street - completed
  • Rednall Street, Tea Tree Gully – Elizabeth Street to Haines Road - completed
  • Renwick Crescent, Tea Tree Gully – Vizard Street to end - completed
  • Vizard Road, Tea Tree Gully – Elizabeth Street to Ellen Street - completed
  • Walter Street, Tea Tree Gully – Haines Road to Harding Street - completed
  • Walter Street, Tea Tree Gully – North East Road to Harding Street - completed
  •  William Street, Tea Tree Gully – Elizabeth Street to Haines Road - completed

Re-sheeting unsealed roads - $126,000

Golden Grove

  • Burg Road, Golden Grove – Hannaford Hump Road to end - completed
  • Falkenburg Road, Golden Grove – One Tree Hill Road to end - completed

Gould Creek

  • Purdom Road, Gould Creek – Burg Road to end - completed

Roads to Recovery - $197,000

This federally funded program to cover the cost of patching and resurfacing this section of road  

Gould Creek

  •  One Tree Hill Road, Gould Creek - delayed until 2019-2020 as this project will be undertaken with Playford Council. Due to the deferment of works on One Tree Hill Road, the funds were allocated to extra resealing work as listed above.