shared use path - Brabham Ave to Parsons Road.jpg

Published 27 September 2019

We’ve got good news for runners, walkers and cyclists with a $200,000 upgrade of a Holden Hill section of O-Bahn Linear Park path to be completed by November 2019.

About 680 metres of deteriorating asphalt path from Brabham Avenue to Parsons Road is being replaced with a three-metre wide reinforced concrete path throughout the section.

Construction work commenced in mid-July 2019 and is expected to be completed by November this year.

In the past four years, Tea Tree Gully Council has invested $745,000 in 4.8 km of O-Bahn Linear Park upgrades, offset by $225,000 in state government funding.

Subscribe to our e-newsletter for more local news

Tags