Burragah Reserve lighting and sportsfield upgrade

Aerial view of the sports field during the day
    Project typeCapital works
    Project value$1,415,000
    Grant fund$282,405
    Project schedule2026 completion
    Contractor nameBeltrame Civil

    Upgrade of the sports field LED floodlighting at Burragah Reserve is now complete. One of the soccer pitches was upgraded as part of the project.

    The $565,000 lighting upgrade was jointly funded by Council and the State Government’s Community Recreation and Sports Facilities Program, while the $850,000 cost to upgrade the pitch was fully funded by Council.

    Project schedule

    • Design: Mid-2024 to late 2024
    • Construction tender: Late 2024 to early 2025
    • Construction: Mid-2025
    • Complete: Early 2026
    Location

    Burragah Reserve, 28/30 Alexander Avenue, Modbury North SA 5092