Kimberley Reserve upgrade

Small reserve bordered by footpath with bench
Project typeCapital works
Project value$315,000
Project schedule2026 completion
Contractor nameLCS Landscapes

The project has delivered

  • installation of a new irrigation system and instant turf
  • an outdoor picnic setting, bench and shelter
  • semi-advanced tree planting
  • three indented car-parking bays.

Project schedule

  • Design: Mid-2025
  • Construction tender: Late 2025
  • Construction: Late 2025 to Early 2026
  • Complete: Early 2026
Location

Kimberley Reserve, 6-8 Kimberley Avenue, Modbury North SA 5092