Elliston Reserve upgrade

Unplanted reserve with dirt bike jumps
    Project typeCapital works
    Project value$4 million
    Grant fund$3 million
    Project schedule2028 completion
    Contractor nameForge Outdoors Pty Ltd

    The upgrades proposed for Elliston Reserve are an important step in the reserve’s recovery after a giant pine scale infestation in 2023.

    The project will deliver:

    • extensive revegetation
    • junior and senior playspaces
    • bike trails, junior pump track, skate plaza and snake run
    • small sports court
    • new outdoor furniture
    • public art
    • on-site car parking
    • public toilet facilities.

    View the full concept masterplan here.

    The examples shown in the concept masterplan are indicative only. The final design, materials and products will be subject to budget considerations and Council's procurement processes.

    Project schedule

    • Design: Mid to late-2026
    • Construction tender: Mid-2026 to late-2026
    • Construction: Early 2027
    • Complete: Mid-2028
    Location

    Elliston Reserve, 953-987 Lower North East Road, Highbury SA 5098