Elysium Reserve upgrade

Playground surrounded by grassed area and trees
Project typeCapital works
Project value$300,000
Project  schedule2026 completion
Contractor namePlotworks

Elysium Reserve is getting an upgrade. The project will deliver:

  • new playspace
  • irrigation upgrade
  • new paths
  • new planting
  • new outdoor furniture.

Project schedule

  • Design: Late 2025
  • Construction tender: Early 2026
  • Construction: Mid-2026
  • Complete: Late 2026
Location

Elysium Drive, Wynn Vale SA 5127