Tea Tree Gully township upgrade

Main road with trees and bicycle tracks lining each side
    Project typeCapital works
    Project value$3.6 million - across two financial years
    Project schedule2026 completion
    Contractor namePlot Works Pty Ltd

    As part of the planned upgrade of North East Road from Church Street through to Haines Road, Council has been working towards the beautification of North East Road.

    The project works include removal of stobie poles and undergrounding of the powerlines. SA Power Network project managing this.

    Additional upgrades commenced in 2025 and include tree planting, streetscaping, reserve improvements, public art and a wombat crossing.

    Read further information regarding Power Line Environmental  Committee (PLEC) works

    Project schedule

    • Design: Late 2024 to early 2025
    • Construction tender: Early 2025 to mid-2025
    • Construction: Mid-2025
    • Complete: Late-2026
    Location

    North East Road (Between Church Street and Haines Road), Tea Tree Gully SA 5091